I have one license for Pix4dmatic, can I process more than one project in the same time?
Hi @licenses2
Thank you for your request.
With a PIX4Dmatic, you can, in theory, open two separate windows and have two processes at the same time with one license. However, the two open windows will compete for the same hardware resource, resulting in an overall processing time higher than the two separate single processes.
What you can do, and what we usually suggest doing, is to queue more projects.
By doing so, the different processes will run one after the other, without the need for someone to hit “start” each time a process ends.
Some of our users use this feature to schedule multiple project processing jobs overnight or on weekends.
You can learn more here:
Let me know if this helps you.
Cheers,
Daniele